The clocks really are counting down in the KTOO production and transmission facilities. Luckily, the clocks and most of the other equipment is installed and working.
Above, in the Master Control Room you see KTOO staff and technicians from BURST working to test all of the equipment and make sure it is communicating and interfacing properly.
This image shows the Production Control Room next to the MCR and one of the BURST project engineers programming and configuring the new digital production equipment. You will notice if you look closely that there are cameras making pictures on the monitors. Some of those images are coming down live from the new cameras in the capitol building.
Everything is on schedule to turn over the fully operational facilities on Wednesday -- just in time for the start of the legislative special session on Thursday morning. Don't you love it when a plan comes together?